In use
NB The 2020 edition of the RIBA Plan of Work has renamed this stage 'Use'.
The process for completing the design and construction of a building is often divided into notional ‘stages’. This can be helpful in establishing milestones for the submission of progress reports, the preparation of information for approval, client gateways, and for making payments. However there is a great deal of ambiguity between the naming of stages by different organisations and the definition of what individual stages include (see comparison of work stages) and so it is important that appointment documents make it clear specifically what activities fall within which stage, and what level of detail is required.
‘In use’ was a new phrase coined by the Royal Institute of British Architects (RIBA) for the 2013 Plan of Work. This plan comprised eight work stages:
- 0 - Strategic definition.
- 1 - Preparation and brief.
- 2 - Concept design.
- 3 - Developed design.
- 4 - Technical design.
- 5 - Construction.
- 6 - Handover and close out.
- 7 - In use.
Stage 7, ‘In Use’ was described by the RIBA as a new stage within the Plan of Work which includes post-occupancy evaluation and post-project review as well as ‘…new duties that can be undertaken during the In Use period of a building.’ Some of these services were previously included in the stages L2: Initial Occupation Services and L3: Post Occupancy Evaluation Services.
The 2020 edition of the RIBA Plan of Work has renamed this stage 'Use'. It suggests that: 'On the majority of projects, the design team and construction team will have no Stage
7 duties to undertake.'
However consultants might provide advice to the client post construction in relation to:
- Letting.
- Rating.
- Maintenance.
- Energy consumption and energy certificates.
- Insurance.
- Tenants queries.
- Facilities management.
- The preparation of tender documents for maintenance and operation contracts.
- Post occupancy evaluation.
- Facilities management.
[edit] Related articles on Designing Buildings Wiki
- Occupation.
- Comparison of work stages.
- Defects liability period.
- Designing Buildings Wiki Project plans.
- Developed design.
- Performance gap.
- Performance in use.
- Post-occupancy evaluation.
- Post-project review.
- RIBA Plan of Work.
- Soft landings.
[edit] External references
Featured articles and news
Villa Wolf in Gubin, history and reconstruction. Book review.
Construction contract awards down £1bn
Decline over the past two months compared to the same period last year, follows the positive start to the year.
Editor's broadbrush view on forms of electrical heating in context.
The pace of heating change; BSRIA market intelligence
Electric Dreams, Boiler Realities.
New President of ECA announced
Ruth Devine MBE becomes the 112th President of the Electrical Contractors Association.
New CIAT Professional Standards Competency Framework
Supercedes the 2019 Professional Standards Framework from 1 May 2025.
Difficult Sites: Architecture Against the Odds
Free exhibition at the RIBA Architecture Gallery until 31 May.
PPN 021: Payment Spot Checks in Public Sub-Contracts
Published following consultation and influence from ECA.
Designing Buildings reaches 20,000 articles
We take a look back at some of the stranger contributions.
Lessons learned from other industries.
The Buildings of the Malting Industry. Book review.
Conserving places with climate resilience in mind.
Combating burnout.
The 5 elements of seiri, seiton, seiso, seiketsu and shitsuke.
Shading for housing, a design guide
A look back at embedding a new culture of shading.
The Architectural Technology Awards
The AT Awards 2025 are open for entries!
ECA Blueprint for Electrification
The 'mosaic of interconnected challenges' and how to deliver the UK’s Transition to Clean Power.